May 25, 2021 Project Update
Sidewalk Updates–Concrete removals have been completed, aside from sections that are slated to be removed and grass re-established.
Driveways and outwalks along 7th Street will be poured Tuesday (5/25) and will continue pouring mainline sidewalk through the week (weather permitting) within the 7th – 14th Street, east of Church Avenue.
Pedestrian ramp construction will continue through the end of the week. Estimated completion of ramps north of 6th Street by the end of the week (weather permitting) and possibly begin working on ramps south of 6th Street midweek.
Street Updates–Concrete removal/replacement of pedestrian ramps and curbs related to street construction project proposed to begin June 7 north of Highway 14.
Trail Updates–Trail paving/construction to begin June 1 with the Hwy 14 section to Catholic church being completed first.