2021 Archived Posts

October 2021 – Project Update

(10/8)

2021 Project Updates.

In a final push to complete the projects, construction crews are working together to coordinate their schedules. Contractors are estimating that all projects will be completed by the end of October, but may be sooner.

Chattanooga Innovation Park

Legends completed the concrete curb and gutter along the extension of Enterprise Drive and Dunn Blacktop completed the first two required lifts of bituminous last Friday and Saturday.  A final lift will be installed in the spring.  This is done to allow for the pavement to settle and to allow for corrections after a winter freeze.

Crosswalks/Trails/Road Striping Project 

A painting crew will begin their process upon completion of the street paving.  Additionally, trail crossings, selected pedestrian crossings, city parking lots requiring painting, and selected streets will be painted over the next several weeks.

Street Project

Both Legends Concrete and Dunn Blacktop have stated that they intend to be in town the week of October 11th and will work to complete the necessary concrete curbing in order for Dunn Blacktop to finish several projects along with completion of the milled streets in town along with finishing any additional patches, etc.

Casting Adjustments

 

Floorcoat Midwest stated they will be working on casting adjustments along Oakview Drive, Northwoods Drive, and E 4th Street this week. If Dunn does not pave anything this week, the crew plans to start adjusting gate valves on streets where they have completed manhole adjustments (Richland Avenue, E 13th Street, E 15th Street, Idso Court, Gladiola Drive, Country View Lane, and Oakview Drive).

Schedules are subject to change, but we appreciate everyone’s patience.

May 25, 2021 Project Update

Sidewalk Updates–Concrete removals have been completed, aside from sections that are slated to be removed and grass re-established.

Driveways and outwalks along 7th Street will be poured Tuesday (5/25) and will continue pouring mainline sidewalk through the week (weather permitting) within the 7th – 14th Street, east of Church Avenue.

Pedestrian ramp construction will continue through the end of the week.  Estimated completion of ramps north of 6th Street by the end of the week (weather permitting) and possibly begin working on ramps south of 6th Street midweek.

Street Updates–Concrete removal/replacement of pedestrian ramps and curbs related to street construction project proposed to begin June 7 north of Highway 14.

Trail Updates–Trail paving/construction to begin June 1 with the Hwy 14 section to Catholic church being completed first.